Spring Garden, St. Croix, USVI

Spring Garden sits on a steep hillside above St. Croix. Below the surface, just inches down, is Blue Bitch — the hardest bedrock in the territory. On the mainland a foundation dig takes a day. On this site, drilling through Blue Bitch on the side of a mountain took weeks. Progress measured in inches, not feet. But here is what most people do not know about Blue Bitch: a structure anchored into it does not move. When Hurricane Maria hit in 2017 with 235 mile per hour winds, this house stood. When the second Category 5 came, it stood again. The same rock that made the build brutal is the reason the house is still there. Mark has been building into Blue Bitch for 27 years. He knows how to fight it — and how to use it.

Owner June Sennon also asked for two major change orders mid-build. The ground floor, originally closed storage, became a full one-bedroom unit with kitchen, bath, living space, and laundry. The roof design changed entirely — from angled to a concrete flat roof with wooden stairs climbing over 50 feet to the top. Both changes were absorbed without stopping the clock. The house was delivered foundation to finish in five months, on budget. It is also fully self-sustainable: a cistern sized for two families and a complete off-grid solar system — installed by the same contractor. Learn more about the solar work at Off Grid Power Hub.

Owner

June Sennon

Location

Spring Garden, St. Croix

Time to complete

5 months

Structure

3 stories — 50ft to roof

"The rock that made it hard to build is the reason it survived two Category 5 hurricanes."

The site

Steep hillside. Blue Bitch bedrock. Equipment access by determination only.

Foundation and ground floor

Drilling into Blue Bitch. One month cure time before the first floor could go up.

First floor

After a month's cure. Three stories taking shape on a hillside.

Second floor and roof

Concrete roof. Wooden stairs climbing 50 feet. The changed design, built right.

Completion

Foundation to finish. Five months. On budget. Two major change orders absorbed. Two Category 5 hurricanes survived.

Site video

Walkthrough from the job site.

Site walkthrough — Spring Garden

Your project deserves the same standard.